Sec. 2205Extension of authority to carry out certain fiscal year 2024 projects

TL;DR

Notwithstanding section 2002 of the Military Construction Authorization Act for Fiscal Year 2024 (division B of Public Law 118—31; 137 Stat.

Statutory text

(a) Extension. Notwithstanding section 2002 of the Military Construction Authorization Act for Fiscal Year 2024 (division B of Public Law 118—31; 137 Stat. 709), the authorizations set forth in the table in subsection (b), as provided in section 2201 of that Act (137 Stat. 714), shall remain in effect until October 1, 2027, or the date of the enactment of an Act authorizing funds for military construction for fiscal year 2028, whichever is later.

(b) Table. The table referred to in subsection (a) is as follows:Navy: Extension of 2024 Project AuthorizationsState/CountryInstallation or LocationProjectOriginal Authorized AmountCaliforniaMarine Corps Air Ground Combat Center Twentynine PalmsCommunications Towers$55,341,000ConnecticutNaval Submarine Base New LondonWeapons Magazine & Ordnance Operations Fac$219,200,000District of ColumbiaMarine Barracks Washington (8th Street and I)Bachelor Enlisted Quarters & Support Facility$131,800,000GuamNaval Base GuamPDI: Consolidated MEB HQ/NCIS Phase II$19,740,000PDI: Satellite Communications Facility (INC)$595,100,000HawaiiMarine Corps Base Kaneohe BayWater Reclamation Facility Compliance Upgrade$318,845,000ItalyNaval Air Station SigonellaEDI Ordnance Magazines$90,348,000MarylandFort MeadeCybersecurity Operations Facility$186,480,000Naval Air Station Pax RiverAircraft Development and Maintenance Facilities$141,700,000North CarolinaMarine Corps Base Camp Lejeune10th Marines Maintenance & Operations Complex$117,550,000VirginiaMarine Corps Base QuanticoWater Treatment Plant$127,120,000Naval Station NorfolkMQ-25 Aircraft Laydown Facility$128,678,000Naval Weapons Station YorktownWeapons Magazines$283,500,000WashingtonNaval Base KitsapAlternate Power Transmission Line$19,000,000

Extension of authority to carry out certain fiscal year 2024 projects (Table 2205)

Extension of authority to carry out certain fiscal year 2024 projects — amounts in thousands of dollars
State/CountryInstallation or LocationProjectOriginal Authorized Amount
CaliforniaMarine Corps Air Ground Combat Center Twentynine PalmsCommunications Towers$55,341,000
ConnecticutNaval Submarine Base New LondonWeapons Magazine & Ordnance Operations Fac$219,200,000
District of ColumbiaMarine Barracks Washington (8th Street and I)Bachelor Enlisted Quarters & Support Facility$131,800,000
GuamNaval Base GuamPDI: Consolidated MEB HQ/NCIS Phase II$19,740,000
PDI: Satellite Communications Facility (INC)$595,100,000
HawaiiMarine Corps Base Kaneohe BayWater Reclamation Facility Compliance Upgrade$318,845,000
ItalyNaval Air Station SigonellaEDI Ordnance Magazines$90,348,000
MarylandFort MeadeCybersecurity Operations Facility$186,480,000
Naval Air Station Pax RiverAircraft Development and Maintenance Facilities$141,700,000
North CarolinaMarine Corps Base Camp Lejeune10th Marines Maintenance & Operations Complex$117,550,000
VirginiaMarine Corps Base QuanticoWater Treatment Plant$127,120,000
Naval Station NorfolkMQ-25 Aircraft Laydown Facility$128,678,000
Naval Weapons Station YorktownWeapons Magazines$283,500,000
WashingtonNaval Base KitsapAlternate Power Transmission Line$19,000,000